Time And Work Ques 11

Question-

A project requires 12 women to complete it in 16 days. 12 women started working and after a few days from the start of the project, 4 women left. If the remaining project was completed in 18 days, in how many days the whole project was completed?

(1) $24 \frac{1}{2}$

(2) 26

(3) 22

(4) $21 \frac{1}{2}$

(5) 20

(IBPS RRBs Officer Scale-I & II CWE 13.09.2015)

Show Answer

Correct Answer: (3)

Solution: (3)

Work done by 8 women in 18 days $=W_{2}$ (let)

$\therefore \frac{M_{1} D_{1}}{W_{1}}=\frac{M_{2} D_{2}}{W_{2}}$

$\Rightarrow \frac{12 \times 16}{1}=\frac{8 \times 18}{W_{2}}$

$\Rightarrow W_{2}=\frac{8 \times 18}{12 \times 16}=\frac{3}{4}$

$\therefore$ Remaining work $=1-\frac{3}{4}=\frac{1}{4}$

This part of work was done by 12 women.

$\therefore$ Time taken by them $=4$ days

$\therefore$ Required time $=18+4$ $=22$ days