Miscellaneous Question 94

In each question, there are two different statements given as Quantity I and Quantity II. You have to consider the statements individually and mark your answer accordingly as per the given codes.

(1) Quantity I $>$ Quantity II

(2) Quantity I $<$ Quantity II

(3) Quantity I $\geq$ Quantity II

(4) Quantity I $\leq$ Quantity II

(5) Quantity I = Quantity II or relationship cannot be established

(IBPS RRBs Officer CWE Prelim Exam, 13.09.2020)

  1. Quantity I : A and B can do a work in $\frac{8}{3}$ days, $B$ and $C$ can do the same work in 3 days and $A$ and $C$ can do the same work in 24 $\frac{24}{5}$ days. In what time $C$ alone can complete the work?

Quantity II : 15

Show Answer

Correct Answer: 94. (2)

Solution: 94. (2) (A+B)’s 1 day’s work

$=\frac{3}{8} \ldots$. (i)

(B + C)’s 1 day’s work

$=\frac{1}{3}$

(C + A)’s 1 day’s work

$=\frac{5}{24}$

On adding all three,

2 (A+B + C)’s 1 day’s work

$=\frac{3}{8}+\frac{1}{3}+\frac{5}{24}$

$=\frac{9+8+5}{24}=\frac{22}{24}=\frac{11}{12}$

$\therefore(\mathrm{A}+\mathrm{B}+\mathrm{C})$ ’s 1 day’s work

$=\frac{11}{24} \ldots$. (iv)

$\therefore$ C’s 1 day’s work = Equation (iv) - (i).

$=\frac{11}{24}-\frac{3}{8}$

$=\frac{11-9}{24}=\frac{2}{24}=\frac{1}{12}$

$\therefore$ Required time

$=12$ days

Clearly, quantity I < quantity II